CASE STUDY · FIELD SERVICES

400 workstations, a live hospital, night shifts.

Staging, imaging, and installing over 400 desktops and laptops across a working children's hospital without interrupting clinical operations.

Client
UCSF Benioff Children's Hospital
Engagement
Field Services
Timeline
3.5 months
Scope
400+ units

Provenance: this engagement was delivered under PM2net, prior to the founding of Megsolve. It was led by Esram Gibran Khan, now Managing Partner at Megsolve, and is presented here as documented delivery experience rather than as a Megsolve client engagement.

400Units deployed
3.5Duration in months
1Rooms consolidated

The opportunity

01 · CONTEXT

UCSF Benioff Santa Rosa was operating on ageing and failing desktops and laptops, causing delays and mismanagement across the site. A full technological overhaul was commissioned.

The project then hit an internal setback. Initial scoping by a field services engineer allocated significantly fewer hours than the work required, overlooking the imaging process for all 400 hardware units entirely. Left unaddressed, that gap would have delivered new hardware into the estate without the standard build on it.

Correcting the scope introduced both complexity and urgency. The objectives remained: upgrade hardware, improve communication tools, prioritise safety, optimise space, standardise software, improve display quality, and integrate it all inside a fixed budget and a tight timeline.

The solution

02 · DELIVERY

A field approach built around the constraint that mattered most: this was a working hospital, and clinical operations came first.

PH 01

Team organisation

  • Team divided by expertise so each member worked to their strengths
  • Skills and resources mapped against the corrected scope
PH 02

Night-time working model

  • Critical installation tasks scheduled overnight to avoid disrupting hospital operations
  • Quieter, more controlled working environment achieved during peak-risk tasks
PH 03

Separated staging and installation

  • Dedicated rooms assigned to staging and to installation to prevent overlap
  • Concurrent workstreams enabled without interference
PH 04

Parallel installation

  • New work model introduced running installation simultaneously across multiple PCs
  • Overall installation time reduced significantly against sequential working
PH 05

Automation and consolidation

  • Automation techniques applied to streamline warehouse operations across the large hospital site
  • Staging and imaging consolidated into a single room for all 400 PCs
  • Waste removal executed off-peak, at night, to minimise interference

The impact

03 · OUTCOME

Problem resolved and estate delivered

Operations protected

Honest accounting

Knowledge retained

Desktop ImagingWorkstation DeploymentStandardised Software BuildAutomationCRM Knowledge Capture
CLOSING NOTE

This one cost more than it earned, and the write-up says so. The scoping error was ours; the fix was absorbing it, delivering all 400 units, and carrying the estimation lessons into everything after it.